Mississippi Power Will Absorb Costs for Failed Kemper Gasification Project
A settlement Mississippi Power reached on August 21 with stakeholders of the Kemper County facility will ensure customers won’t be subjected to rate increases associated with the now-abandoned gasification portion of the project. While that will affect revenues, the resolution could soften controversy surrounding the project and avoid protracted legal and financial turmoil, the company said.
Mississippi Power reached the settlement with Denbury Resources—the company under contract to buy all the project’s captured carbon, and which had already built a 61-mile carbon dioxide pipeline—along with three advocacy groups: the Central Mississippi Building and Construction Trades Council, the East Mississippi Business Development Corp., and the Ministerial Alliance Partnership.
It essentially provides that the annual revenue requirement—which is necessary to cover the power company’s expenses and have the opportunity to earn a fair rate of return—for the 2018 Kemper IGCC–related costs would be $ 126 million, resulting in no rate increase for customers now or in the future. It also proposes to modify the project’s 2010-awarded certificate of public convenience and necessity to limit the facility to operations of the natural gas combined cycle power plant, which was completed in 2014.…