Is Vogtle Nuclear Expansion on Schedule? CEO Sounds Confident
The post Is Vogtle Nuclear Expansion on Schedule? CEO Sounds Confident appeared first on POWER Magazine.
“We still expect to meet the November regulatory-approved in-service dates for both Units 3 and 4,” Southern Company CEO Tom Fanning said during the company’s first quarter earnings call on April 30. The in-service dates he was referring to are November 2021 and November 2022 for Units 3 and 4, respectively, at the Vogtle nuclear expansion project near Waynesboro, Georgia. The project is owned by four partners: Southern Company subsidiary Georgia Power (45.7%), Oglethorpe Power Corp. (OPC, 30%), Municipal Electric Authority of Georgia (MEAG Power, 22.7%), and Dalton Utilities (1.6%).
Furthermore, Fanning said site managers continue to believe they can hit target dates set in the company’s “Aggressive Site Workplan,” which are May 2021 and May 2022, respectively. “Is it riskier than it was before? Yeah. But it’s still a reasonable objective; otherwise, we wouldn’t stick with it,” said Fanning.
Significant Progress Made on Both New Vogtle Units
About two weeks ago, Southern Company announced it would reduce the workforce on the project by 20% in an effort to mitigate the impacts of COVID-19.…