Fuel Loading Only Major Milestone Left for Vogtle Unit 3 Nuclear Project
The post Fuel Loading Only Major Milestone Left for Vogtle Unit 3 Nuclear Project appeared first on POWER Magazine.
Tom Fanning, CEO of Southern Company, reported during the company’s earnings call on July 29 that hot functional testing (HFT) had been completed on Vogtle Unit 3, and that the “next and final major milestone” is fuel load. “We project fuel load to occur sometime near year-end 2021 or early in 2022,” he said.
The Vogtle nuclear power plant expansion project includes the addition of two new Westinghouse AP1000 reactors—Units 3 and 4 at a site near Waynesboro, Georgia, that has two existing units. (Unit 1 began operation in 1987 and Unit 2 began operation in 1989.) The project is owned by four partners—Southern Company subsidiary Georgia Power (45.7%), Oglethorpe Power Corp. (30%), Municipal Electric Authority of Georgia (MEAG Power, 22.7%), and Dalton Utilities (1.6%).
Construction on Unit 3 and 4 has been a long, drawn-out process. Southern Nuclear (a subsidiary of Southern Company) filed for an early site permit (ESP) application with the Nuclear Regulatory Commission (NRC) in August 2006.…