Kemmerer 1—TerraPower’s Pioneering Fourth-Generation Nuclear Project—Hits Key NRC Milestone Ahead of Schedule

February 27, 2025
| No Comments
| Industry News

The U.S. Nuclear Regulatory Commission (NRC) has completed its draft safety evaluation (SE) a month ahead of schedule—albeit with open items—for TerraPower’s Kemmerer Power Station Unit 1, a pioneering 345-MW […]

The post Kemmerer 1—TerraPower’s Pioneering Fourth-Generation Nuclear Project—Hits Key NRC Milestone Ahead of Schedule appeared first on POWER Magazine.

A bird's eye view of TerraPower's Natrium advanced nuclear reactor plant.

POWER Magazine…

Read More »

Offshore Wind Milestone: China’s Dongfang Unveils 26-MW Turbine

October 14, 2024
| No Comments
| Industry News

Chinese state-owned manufacturer Dongfang Electric announced the company has completed production of a 26-MW offshore wind turbine, continuing a trend of ever-more-powerful turbines from that country. The turbine’s nacelle, shown […]

The post Offshore Wind Milestone: China’s Dongfang Unveils 26-MW Turbine appeared first on POWER Magazine.

Dongfang 26 MW October 2024

POWER Magazine…

Read More »

Fuel Loading Only Major Milestone Left for Vogtle Unit 3 Nuclear Project

July 30, 2021
| No Comments
| Industry News

The post Fuel Loading Only Major Milestone Left for Vogtle Unit 3 Nuclear Project appeared first on POWER Magazine.

Tom Fanning, CEO of Southern Company, reported during the company’s earnings call on July 29 that hot functional testing (HFT) had been completed on Vogtle Unit 3, and that the “next and final major milestone” is fuel load. “We project fuel load to occur sometime near year-end 2021 or early in 2022,” he said.

The Vogtle nuclear power plant expansion project includes the addition of two new Westinghouse AP1000 reactors—Units 3 and 4 at a site near Waynesboro, Georgia, that has two existing units. (Unit 1 began operation in 1987 and Unit 2 began operation in 1989.) The project is owned by four partners—Southern Company subsidiary Georgia Power (45.7%), Oglethorpe Power Corp. (30%), Municipal Electric Authority of Georgia (MEAG Power, 22.7%), and Dalton Utilities (1.6%).

Construction on Unit 3 and 4 has been a long, drawn-out process. Southern Nuclear (a subsidiary of Southern Company) filed for an early site permit (ESP) application with the Nuclear Regulatory Commission (NRC) in August 2006.…

Read More »

Offshore Milestone as Feds Back Vineyard Wind Project

May 12, 2021
| No Comments
| Industry News

The post Offshore Milestone as Feds Back Vineyard Wind Project appeared first on POWER Magazine.

The first large-scale offshore wind farm in the U.S. has received the go-ahead from the federal government, with industry insiders saying the milestone decision is likely to spur more rapid development of the nation’s offshore wind projects.

The Vineyard Wind installation, an 800-MW project that will use GE’s Haliade-X turbines, on May 11 received the Record of Decision (ROD) from the U.S. Dept. of the Interior’s Bureau of Ocean Energy Management (BOEM). The ROD is the last major step in the federal review process for Vineyard Wind, a joint venture of Avangrid Renewables, a subsidiary of AVANGRID, and Copenhagen Infrastructure Partners (CIP).

“Today’s Record of Decision is not about the start of a single project, but the launch of a new industry,” said Vineyard Wind CEO Lars T. Pedersen in a statement. “Receiving this final major federal approval means the jobs, economic benefits and clean energy revolution associated with the Vineyard Wind 1 project can finally come to fruition.”…

Read More »

MHPS Marks Third Major U.S. Gas-Turbine Milestone in Recent Months

August 31, 2018
| No Comments
| Industry News

NTE Energy on August 28 formally began operations of its 475-MW Kings Mountain Energy Center (KMEC) natural gas–fired plant in Cleveland County, North Carolina, marking the third major milestone in recent months for gas-turbine giant Mitsubishi Hitachi Power Systems (MHPS) Americas.

The $ 500 million KMEC facility features MHPS G-Series advanced-class gas turbine technology. Owned and operated by NTE Carolinas LLC, KMEC began operations three months after NTE Energy opened its 525-MW Middletown Energy Center in Butler County, Ohio, which also features MHPS G-Series technology. That plant is powered by a M501GAC gas turbine and technology in a combined cycle alignment. 

On August 23, MHPS also announced successful first fire for Dominion Energy’s 1,558-MW Greensville County Power Station located in Emporia, Virginia. That plant operates three M501J gas turbines supplied by Mitsubishi. The three J-Series turbines, which MHPS said “are the cornerstone of the largest and cleanest gas-fired power block ever operated inside the U.S,” are the first to come online in the U.S.…

Read More »