Vogtle Start Dates Pushed Back Again
Georgia Power has again pushed back the in-service dates for two new reactors at the Vogtle nuclear power plant, with Units 3 and 4 now projected to come online in the third quarter of 2022 and the second quarter of 2023, respectively.
Georgia Power in an Oct. 21 news release said its needs more time to deal with continued issues with construction, and to conduct more comprehensive testing to ensure quality and safety standards are met at the two-unit expansion project in Waynesboro, Georgia. The U.S. Nuclear Regulatory Commission in late August said it would consider increasing oversight of the oft-delayed project.
It’s the fourth time in just the past six months that Georgia Power has announced a further delay in startup of the two units.