Vogtle Expansion Cost Jumps Again; In-Service Dates Set for 2023

July 28, 2022
| No Comments
| Industry News

Southern Co. on July 28 increased its cost estimate for Georgia Power’s share of the two-unit expansion of the Vogtle nuclear plant.

Southern, during an investor presentation of the company’s second-quarter financial results, said Georgia Power’s share of capital costs for the project has risen by $ 52 million, to about $ 10.5 billion in total. Georgia Power, the largest of four utilities owned by Southern Co., owns 45.7% of the project. The construction of Units 3 and 4 at Vogtle is years behind schedule, and the project’s price tag has ballooned to more than $ 30 billion, according to energy industry analysts.

The Vogtle expansion is adding two 1,117-MW Westinghouse AP1000 reactors to two existing units at the site in Waynesboro, Georgia. The project, when initially approved in 2009, was expected to cost about $ 14 billion, with the new reactors coming online in 2016 and 2017. Myriad issues have contributed to delays for the project, including the bankruptcy of Westinghouse and the coronavirus pandemic.…

Read More »

Vogtle Start Dates Pushed Back Again

October 23, 2021
| No Comments
| Industry News

Georgia Power has again pushed back the in-service dates for two new reactors at the Vogtle nuclear power plant, with Units 3 and 4 now projected to come online in the third quarter of 2022 and the second quarter of 2023, respectively.

Georgia Power in an Oct. 21 news release said its needs more time to deal with continued issues with construction, and to conduct more comprehensive testing to ensure quality and safety standards are met at the two-unit expansion project in Waynesboro, Georgia. The U.S. Nuclear Regulatory Commission in late August said it would consider increasing oversight of the oft-delayed project.

It’s the fourth time in just the past six months that Georgia Power has announced a further delay in startup of the two units.

“As we’ve said from the beginning of this project, we are going to build these units the right way, without compromising safety and quality to achieve a schedule deadline,” said Chris Womack, chairman, president and CEO of Georgia Power, in a statement.…

Read More »