EDF Announces More Delays, Cost Overruns for Flamanville 3 Reactor
French utility Électricité de France (EDF)on July 25 said it has pushed fuel loading at its 1.6-GW Flamanville 3 nuclear project to the fourth quarter of 2019 and increased cost estimates for the project by another €400 million (USD $ 467.1 million).
EDF said its current cost for the project has ballooned to €10.9 billion (USD $ 12.75 billion), triple the original budget. The utility today said start-up for the troubled EPR reactor will not occur until at least the second quarter of 2020. Fuel loading and commercial operation start dates at the Normandy plant have now been revised twice in the past year; in October 2017, EDF said fuel loading was set for late 2018, with full production in 2019.
EDF said the latest delay is due to faulty welding of joints, which the utility had previously discussed in April and May of this year. The utility said it has inspected 148 of 150 welds in the main secondary system at Flamanville 3 and found 33 needed repairs.…