Watts Bar Unit 2 Nuclear Plant Completes Power Ascension Testing

October 4, 2016
| No Comments
| Industry News

The Tennessee Valley Authority (TVA) has reached another milestone in its effort to bring Watts Bar Unit 2 into commercial operation: The unit completed its final power ascension test—a 50% load rejection from full power—and safely returned to full power on September 30.

The testing had been halted on August 30 due to a switchyard transformer fire. Although the fire did not affect Unit 2’s systems, which responded to the event as designed, the affected transformer had to be replaced before testing could resume. The TVA said a rigorous and detailed inspection, repair, and testing process was performed before the transformer was returned to service on September 26.

Power ascension testing included more than 40 required tests at various power levels up to 100% output, with pauses at 30%, 50%, and 75% (Figure 1). The gradual increase in power provided data, which was used to verify that the unit was operating as designed.




1. Watts Bar Unit 2 power ascension testing plan.
…

Read More »

Watts Bar Unit 2 Nuclear Plant Synchronized to Power Grid

June 7, 2016
| No Comments
| Industry News

The Tennessee Valley Authority (TVA) reached another milestone on June 3 when operators at Watts Bar Unit 2—the nation’s newest nuclear power plant and the first added to the fleet in 20 years—synchronized its generator to the power grid, generating electricity from the plant for the first time (Figure 1).



1. Reactor Operator Bill Hahn synchronizes Watts Bar Unit 2 to the TVA power grid on Friday, June 3, 2016. Courtesy: TVA

Watts Bar Unit 2 has had a long and storied history. Ground was broken for the plant in 1973. However, construction was suspended in 1985 due to slower electricity demand growth, rising construction costs due to inflation and new regulatory requirements stemming from the accident at Three Mile Island in 1979, and regulatory concerns throughout the TVA nuclear fleet. At the time, Unit 2 was estimated to be about 80% complete with a total investment of about $ 1.7 billion.

In the years that followed, various pieces of equipment, such as pumps, motors, and valves, were salvaged for use in Watts Bar Unit 1 or in Watts Bar’s sister plant, Sequoyah.…